Company |
LACC |
Location |
Lake Charles, Louisiana |
Project |
Loading Terminal |
Services |
Full Service – Design/Construct |
Product |
Chemical |
Capacity |
2 – 6 Spot Railcar |
Status |
Completed in 2012 |
When Liquid Transfer Group became involved, a feed study was already underway and the project had bounced around between outside engineering firms.
The customer was unclear on what solutions were required to expand the chemical company’s product line. We were able to assist the engineering firm to complete a design and manage the build and installation when it came time to execute the plan. With our extensive industry experience, we designed the loading, control, mechanical, and electrical systems and supplied all materials required to complete 2 6-spot rail racks at the loading terminal. Another successful collaboration for LTG.
Download Case Study